The brief
Waterproofing you only get one chance to install.
The service pits at Truckstops’ new Tauriko facility sit below ground, under the trucks and under the slab — once the concrete is poured, there is no going back to fix the membrane.
We installed Sika Sikaproof A+12 and P12 beneath the truck pits: a fully bonded pre-applied membrane that the slab is cast directly against, so water cannot track between membrane and concrete.
Every lap and detail was inspected and photographed before the pour, sequenced tight against Iline’s concrete programme.
Scope of works
Sika Sikaproof A+12 & P12 pre-applied membrane Installation beneath truck service pits Lap and penetration detailing Pre-pour inspection and photographic record Sequenced with the concrete programme Producer statement on completionHow we did it
Sequenced around the main contractor, not the other way round.
01
Sequencing
Booked in against the pour dates so the membrane never held up the concrete crew.
02
Membrane install
Sikaproof laid and lapped across the pit formation, fully bonded to the fresh slab.
03
Detailing
Penetrations and junctions detailed by hand — the part that decides a below ground job.
04
Pre-pour sign off
Every detail inspected and photographed before the slab went down over it.