Mount Maunganui Fire Station
Roof overlay and deck membrane on a working fire station — with the station fully operational throughout.
Main contractor
Marra Construction
Architect
APG Architects
Client
Fire and Emergency NZ
Location
Mount Maunganui
Systems
Sealco · Viking
The brief
A station that could not close, and a roof that could not wait.
Water ingress at the roof and upper deck needed fixing as part of wider strengthening works — on a building that had to stay operational around the clock.
We installed a Sealco single layer torch on overlay to the roof area and Viking Enviroclad TPO at 1.5mm thick to the deck, sequencing hot works around the station’s operations with Marra Construction.
Hot works permits, fire watch and a documented shutdown every day — non-negotiable on any job, and doubly so on a fire station.
Scope of works
Sealco single layer torch on overlay to roof Viking Enviroclad TPO 1.5mm to deck area Hot works permits and daily fire watch Upstand and penetration detailing Sequencing around a 24/7 operational station Photographic QA record and sign offHow we did it
Sequenced around the main contractor, not the other way round.
01
Access planning
Work zones and hot works agreed with Marra and the station so trucks could always respond.
02
Roof overlay
Sealco torch on overlay installed over the existing roof, detail by detail.
03
Deck membrane
Viking Enviroclad TPO welded across the upper deck and terminated at the upstands.
04
Test and sign off
Laps probe tested, photographed and signed off as part of the strengthening works.